Monday, 17 February 2014
Chimneys
With the visual inspection of the boiler complete, a steam test is required. Since the original boiler chimney had to be removed due to a large amount of corrosion, the temporary aluminium one (a sheet rolled, pop riveted and slid down the inside of the cast chimney base) lasted a few steamings but eventually got damaged in the wind. So this Sunday saw temporary chimney number two erected. Made from a peice of donated 600mm spiral wound ducting, the original chimney flanges have been bolted on and the whole thing proped up. Let's hope that we don't see anymore of these storms! It actually looks quite good and might get a paint of black to help it blend in. Temporary at Westonzoyland normally means years! Report to come later on how it does in its test run.