Roofing

Things have progressed well with the facilities extension in the last week. Having purchased all the materials it was decided our volunteers lacked the time or physical strength to get the job done so the builder who put the block work up for us has been contracted to carry out the roofing. The pictures below show what three and half days of labour gets you! We had enough spare tiles for one side and had to purchase new tiles for the other. The three rooflights provide natural light and ventilation to the three toilets below, two public and one volunteer. Work left to do includes the flashings to the existing roof, finish ridge tiles, render the end gable. Our volunteers are going to carry out all the painting required before the scafold is removed in two weeks time. Guttering will then be put up, down pipes will be temporary until rendering is carried out later in the year. 