Monday 10 February 2014

Winter Programme Update

With the rain still falling and the water level rising across large areas of the Somerset Levels our volunteers are still progressing with the projects in hand.

Having had a scrap skip delivered to the museum, this has now been filled to the brim and taken away. As part of the clear up operation some unused equipment was sold off, including two large Broom and Wade compressors. All these funds will be reinvested in new equipment. Our ride on lawn mower requires a new cutting deck, some areas of fencing need replacing and we have purchased a new compressor to start the Crossley Diesel engine. This compressor is single phase and has a max working pressure of 360psi. We only require 250 but means we won't be running it to its limit. All that is required now is to wire it in, get our 600psi tank tested and installed. After nearly two years out of action it should be seen running again in time for April.

With the high winds experienced again over the last week. A large area of brittle trees had fallen over so these have been cut down and turned into logs for the wood burner. Once the ground drys up further winter trimming will be progressed to get the place tidied up before the new season starts.

In order to begin steaming again the boiler needs its annual inspection and certification so the boiler was stripped down and washed out, inspection is imminent. Once visually inspected, it all gets put back together and a steam test is carried out in order to prove safety valve settings etc.

Whilst all this activity was happening, on the opposite side of the engine rhyne the Environment Agency and a private pump hire company were busy setting up two large diesel pumps. These are rated at 60 tonnes per minute each. Why they are putting them in is a 500 page book in itself so I won't go into it! 





1 comment:

  1. You are all doing a great job down at wesonzoyland..

    ReplyDelete